Announcements

Worton Park Road Improvement Update

Thursday, August 24, 2017

Worton Park Update (Oct 12):

Site restoration is scheduled to begin this week.  Driveway apron installation is scheduled for next week (Oct 16-20) and pavement repair will begin during week of Oct 23.  The Service Director advises that it will be difficult to pick up leaves without disturbing freshly restored areas.  Please place raked leaves behind the restored area and Service Dept. personnel will do their best to pick them up without causing any damage.

Water Main Replacement
Worton Park Neighborhood
PROJECT UPDATE - October 2nd, 2017

South Woodlane:

It will be necessary for us to shut off your water from 9:00 AM-4:00 PM on Monday, October 2, 2017 . When your water use is restored, we recommend running cold water for approximately 15 minutes prior to use of hot water. We hope that you understand this is a necessary inconvenience,if you have any questions or concerns please call Jim at DiGioia Suburban Excavating,440-237-1978 x 241

Worton Park/Hemingway:

It will be necessary for us to shut off your water from 9:00 AM-4:00 PM on Wednesday, October 4, 2017 .When your water use is restored, we recommend running cold water for approximately 15 minutes prior to use of hot water. We hope that you understand this is a necessary inconvenience, if you have any questions or concerns please call Jim at

DiGioia Suburban Excavating,440-237-1978 x 241.

Road Improvement & Water Main Replacement
Worton Park Neighborhood

PROJECT UPDATE - September 21, 2017

Contractor DiGioia-Suburban advises that the connection of all homes to the new water main will be complete by Sept 30. Restoration, including drive apron replacements, where needed, pavement repair and final landscaping should be substantially complete in the following three weeks, between Oct 20 and Oct 27.

If you have questions, please contact Engineer Tom Cappello at 216-731-6255 or Service Director Doug Metzung at 440-442-5506.